Environmental clearance of the project received in Feb., 2018.
'Commencement of works' ceremony of TFL inaugurated by Hon'ble Prime Minister in Sept., 2018.
Investment approval of the project has been accorded in Aug., 2019.
M/s Wuhuan Engg. Co. Ltd, China has been engaged as LSTK contractor for Coal Gasification and Ammonia/Urea packages of the project in Sept. 2019. Site activities has started.
Consent to Establish and Consent to Construct obtained.
Water has been allocated to the project in May 2020.
Construction water and construction power system charged and site has been handed over to M/s Wuhuan.
Concession Agreement for transfer of land executed by TFL and FCIL on 29th Jan. 2021.
Urea policy approved by CCEA on 20th April 2021.
Commitment of nearly Rs. 8500 cr. already done.
CISF has been inducted at TFL site.
Sl.
Description
1
Natural Gas sale agreement signed with M/s GAIL in Dec-2023
2
Ash void allocated in Apr-2023
3
Long-term coal linkage allocated in Apr-2023
4
Debt drawl of Rs approx. 9000 Cr. commenced in Dec-2022
5
MoU signed with IOCL for supply of Pet coke in Oct-2021
6
Complete upfront equity (65% of the project capex) from promoters i.e. INR 2,416 cr. approved in Jun-2021
7
Urea policy for project formulated by DoF in Apr-2021